Connecting a production plant
On this page, you can find information about connecting your microgeneration to the electricity network.
Basic information
If you want to connect your microgeneration to the network, you must submit the required notifications. The electrical contractor must provide the network company with the equipment information in accordance with the instructions below. We will ask for further information about the equipment when we are processing the notifications, when necessary. You can start using the equipment only after we have granted the commissioning permit.
Please fill in the information carefully to ensure the commissioning goes ahead smoothly.
Connecting microgeneration equipment (50 kVA or less)
Fill in and sign the microgeneration basic information form (pdf).
Send the information form through the contact form at least two weeks before the planned commissioning.
Connecting microgeneration (50 kVA of more)
Fill in and sign two different forms: the microgeneration basic information form (pdf) and commissioning inspection report (pdf)
Send the forms through the contact form.